Hers is a great picture of the view from the main living area to the west through that covered patio. Snowbasin ski resort is behind the trees.
Work progresses nicely. The main electricity should be hooked up today and then we can use the electric garage doors to get in the house. The heat is operating and the drywall guys have a few more days of work left. When they are done the finish carpenter will install the paint grade wood in closets, window sills, etc. He expects this to take a week or so. Then the painters get started on the inside. That should take two weeks which will be around Christmas. The wood and tile floors should be installed right after the paint. Then it is on to cabinets.