Thursday, August 30, 2007
BIG WEEK
This week we gained a garage, complete with concrete floor, finished the exterior framing on the main level and the drain pipes are also done.
Next week we expect the roof trusses to arrive and start going up. The interior walls will also be partially assembled. We are waiting on a dozen huge beams to complete the interior roof structure. The beams are 12" by 12" and should give the house a rustic look and feel. We expect the interior walls, beams and roof trusses to be done in two weeks, then the roof will be clad in plywood.
The windows will follow and should be installed in a few weeks, then the house will essentially be waterproof.
Wednesday, August 29, 2007
Drains getting close
Monday, August 27, 2007
Friday, August 24, 2007
Framing continues
The main level is taking shape. The exterior walls should be done in a couple of days an the interior walls in a week and a half. The steps into the basement will be installed next week. The roof trusses arrive in a week and they will take a fews days to erect. We can finally stand on the floor of the main level and "picture" what the rooms sizes will be, instead of looking at a blueprint.
We had one surprise today. The ceiling in the dining room will be 14'. We thought it was 10' but the framing looked too high. So we went back and looked at the detailed framing plans and 14' it is. Very cool.
Wednesday, August 22, 2007
Sunday, August 19, 2007
Storm Clouds in the canyon
Wednesday, August 15, 2007
The walls go up
Monday, August 13, 2007
Foundation drains installed
We have two types of drains in in the ground by the foundation. The first is the rain gutter drainpipe which will capture all of the rainwater off the roof and send it to the public storm drain system.
The second is a foundation drain that is perforated and will capture all the water in the ground right next to the house. The purpose of this one is to get all groundwater away from the foundation and into the storm drain system. Both of these drainage systems are required because of the severe slope on the lot.
Friday, August 10, 2007
Thursday, August 2, 2007
Basement floor "flatwork" done
Wednesday, August 1, 2007
The grading begins
The guy who is grading the property also knocked down a couple of trees for us with is huge backhoe. We asked him to knock them down so we did not have to cut them down. In the process he disturbed a beehive inside one of the trees. Thousdand of bees swarmed around him. Fortunately he has an enclosed cab in the backhoe. Unfortunately the air condidtioning did not work and it was 98 degrees. It took a half an hour for the bees to disapate which allowed him to get out of the hot cab!
Subscribe to:
Posts (Atom)